The production of concrete segments for “Caltanissetta” tunnel is completed

Posted: 13 March 2017

SICEP has produced  the concrete segments for “Caltanissetta” tunnel, part of adaptation to 4 lanes of SS 640, Agrigento-Caltanissetta route.

35.856 concrete segments  have been produced, corresponding  to:

  •  3.984 complete rings;
  • 210.033 CM of concrete produced.

The full capacity daily production was 27  segments per shift, corresponds to  9 complete rings  per day and  to 475 CM of concrete produced per day.

At the end of production each formwork has accomplished 966 complete cycles.

SCHEMA CONCI

Sicep achieved from the certification institute ICMQ the CE Marking for concrete precast segments for tunnel.