News

Share

THE SICEP HAS COMPLETED THE ASSEMBLY OF “MALL OF SOUSSE”

Posted: 15 March 2018

Mall Of Sousse, the numbers of a challenge:

  • 14 600 square meters of prefabricated floors;
  • Totally prefabricated administration block with 16 meters long-range slabs on 5 floors;
  • Pillars of the administration block 23 meters high, each produced in one piece;

 

  • 107 pillars;
  • 715 prefabricated pieces;

 

  • 3325 m3 production of prefabricated elements;
  • Production in 110 workdays;
  • Production start date: October 19th, 2017;

 

  • Assembly on site – starting date : December 18th, 2017;
  • Assembly on site – ending date : March 3rd, 2018;

 

  • Assembly time : 57 workdays;
  • Assembly teams : 2;
  • Cranes : 2 (120 tons and 200 tons)
  • Average number of pieces assembled per workday : 13

 

© 2023 SICEP S.p.A. tutti i diritti riservati - P.IVA 03776850871